Part II: 1695-1710 MHz Band (AWS-3)

October 16, 2024

On March 20, 2013, the FCC announced its plan to commence an auction of the 1695-1710 MHz and 1755-1780 MHz frequency bands, which were allocated for federal use, and the 2155-2180 MHz band, which was allocated for non-federal use. These frequencies would be designated as the AWS-3 bands.

On May 13, 2014, NTIA sent a letter to the FCC on behalf of eligible federal agencies, providing notification of the initial estimated relocation and sharing costs and the estimated transition and spending timelines for the 1695-1710 MHz and 1755-1780 MHz bands. The total estimated relocation and sharing costs for the 1695-1710 MHz were $527.1 million.

On September 8, 2014, OMB, in consultation with NTIA, submitted a report to Congress detailing its intent to transfer pre-auction planning funds in the amount of $479,000 to two federal agencies. The AWS-3 auction commenced on November 13, 2014, and concluded on January 29, 2015, with $41.3 billion in net winning bids and a total of 31 bidders winning 1,611 licensees. On June 23, 2015, OMB submitted a second report to Congress detailing its intent to transfer $526.56 million to five federal agencies.

Agencies are expected to adhere to their approved transition plans. Required updates in costs or timelines are subject to OMB and/or NTIA approval. All five agencies (the Department of Commerce (DOC) (National Oceanic and Atmospheric Administration (NOAA)), the Department of Defense (DOD) (United States Air Force (Air Force), Department of the Army (Army), Department of the Navy (DON)), and the Department of Interior (DOI)) reported they have transitioned the use of the spectrum but will continue to use funds from the SRF until achieving comparable capability. NTIA will notify the FCC when each of the agencies has 
completed its transition effort and achieved comparable capability. For the period ending September 2023, outlays for the eligible federal agencies totaled $60.7 million. This brings the total cumulative outlays to $361.6 million.

The following is the overall summary and agency status of funds tables for the 1695-1710 MHz 
band. As all agencies have completed their spectrum transitions, there are no status of spectrum 
transition tables.

1695-1710 MHz Band Summary of Sharing and Relocation Activities

Department/AgencyBureauEstimated 
Completion of
Transition Timeline
(Month/Year)
Transition
Status
Total Original
Estimated
Transition Cost
Total Adjusted
Estimated
Transition Cost
Total
Transferred
From SRF
Cumulative
Outlays
Spending Status
DOCNOAA4/2018Complete$263,303,000$310,309,000$310,303,000$232,653,200Ongoing
DODAir Force4/2018Complete$88,976,400$35,184,300$19,761,500$14,100,100Ongoing
DODArmy4/2018Complete$64,121,000$64,121,000$48,683,300$48,146,400Ongoing
DODNavy4/2018Complete$76,344,500$53,148,000$41,630,300$25,807,800Ongoing
DODSubtotal  $229,441,900$152,453,300$110,075,100$88,054,300 
DOIDOI4/2018Complete$34,325,000$64,805,000$64,801,800$40,868,700Ongoing
Total   $527,069,900$527,567,300$485,179,900$361,576,200 

 

1695-1710 MHz Band Agency Status of Funds

Department of Commerce

National Oceanic and Atmospheric Administration (NOAA)

STATUS OF SPECTRUM RELOCATION FUNDS
System/Program NameOriginal
Estimated
Transition
Costs
Adjusted
Estimated
Transition
Costs
SRF
Transfers
This
Reporting
Year
Total SRF
Transfers
Adjusted
System
Total
Cost Incurred
this Reporting
Year(Outlays)
Cumulative
Outlays
SRF BalanceSystem
Spending
Closeout
Date
Spending
Status
Barrigada GU RCVR Site$15,047,000$0$0$15,047,000$0$0$0$0 N/A
BARROW POES RCVR$7,194,000$0$0$7,194,000$0$0$0$0 N/A
Boulder CO RCVR Site$6,566,000$0$0$6,566,000$0$0$0$0 N/A
Coordination Portal$6,600,000$11,000,000$4,400,000$11,000,000$4,578,200$799,000$9,220,800$3,779,2006/30/2027On Time
Elmendorf AFB-Anchorage POES RCVRS$11,464,000$0$0$11,464,000$0$0$0$0 N/A
Elmendorf AFB-Anchorage POES RCVRS$11,464,000$0$0$11,464,000$0$0$0$0 N/A
FAIRBANKS POES RCVR$12,918,000$0$0$12,918,000$0$0$0$0 N/A
Fairmont WV RCVR Site$6,296,000$0$0$6,296,000$0$0$0$0 N/A
FORD ISLAND POES RCVR$7,683,000$24,875,000$8,875,000$16,558,000$24,875,000$5,373,000$5,373,000$19,502,0006/30/2027On Time
GILMORE CREEK POES RCVR$0$0$0$0$0$0$0$0 N/A
GOES-R Redesign$3,690,000$3,690,000$0$3,690,000$0$0$3,690,000$07/30/2015Complete
GREENBELT GOES RCVRS$3,423,000$0$0$3,423,000$0$0$0$0 N/A
Guaynabo PR RCVR Site$5,202,000$0$0$5,202,000$0$0$0$0 N/A
Hub (NSOF)$34,128,000$52,608,000$16,851,000$50,979,000$32,821,000$6,583,000$26,371,000$26,238,0006/30/2027On Time
KANSAS CITY POES RCVR$3,501,000$0$0$3,501,000$0$0$0$0 N/A
MIAMI AOML POES RCVR$3,253,000$14,754,000$6,250,000$9,503,000$14,017,300$3,893,000$3,893,000$10,124,3006/30/2027On Time
MIAMI NHC POES RCVR$3,386,000$0$0$3,386,000$0$0$0$0 N/A
MONTEREY POES RCVR$3,520,000$0$0$3,520,000$0$0$0$0 N/A
Norman OK RCVR Site$3,482,000$0$0$3,482,000$0$0$0$0 N/A
Pre-Acquisition/GCs & Fees$5,537,000$90,772,000$0$5,537,000$0$0$90,771,700$06/30/2027On Time
Radiosonde Relocation$80,139,000$86,239,000$6,100,000$86,239,000$23,742,300$6,466,000$66,962,700$17,276,3006/30/2027On Time
STENNIS SPACE CENTER POES RCVR$4,867,000$0$0$4,867,000$0$0$0$0 N/A
SUITLAND POES RCVRS$15,056,000$0$0$15,056,000$0$0$0$0 N/A
WALLOPS ISLAND RCVRS (POES/GOES)$20,351,000$26,371,000$4,524,000$24,875,000$7,313,000$6,583,000$26,371,000$730,0006/30/2027On Time
Total$263,303,000$310,309,000$47,000,000$310,303,000$107,346,800$29,697,000$232,653,200$77,649,800  

 

Department of Defense (DOD)

Air Force

STATUS OF SPECTRUM RELOCATION FUNDS
System/Program NameOriginal
Estimated
Transition
Costs
Adjusted
Estimated
Transition
Costs
SRF
Transfers
This
Reporting
Year
Total SRF
Transfers
Adjusted
System
Total
Cost Incurred
this Reporting
Year(Outlays)
Cumulative
Outlays
SRF BalanceSystem
Spending
Closeout
Date
Spending
Status
1695-1710 MHz Portal (ITS)$2,220,000$2,220,000$621,600$1,780,900$1,117,600$886,000$1,484,100$231,6008/14/2025On Time
AF Implementation and Oversight$1,500,000$1,500,000$0$833,700$700,700$246,000$276,000$454,7008/14/2025On Time
AF METSAT 1$5,434,000$5,434,000($260,300)$2,730,300$1,449,700$1,153,000$2,311,600$296,7008/14/2025On Time
AF METSAT 2$13,691,400$6,700,000($260,300)$4,273,200$2,294,200$2,033,000$2,977,400$261,2008/14/2025On Time
AF METSAT 3$18,423,000$6,700,000$299,500$4,833,000$3,181,500$1,460,000$2,404,400$1,721,5008/14/2025On Time
AF METSAT 4$27,900,700$6,917,800($285,600)$4,417,700$2,623,400$1,512,000$2,488,700$1,111,4008/14/2025On Time
AF METSAT Pre-Auction$100,000$100,000$0$71,000$0$0$0$09/14/2015Complete
Monitoring Hub$19,707,300$5,612,500$216,500$4,057,100$2,932,300$1,348,000$2,157,900$1,584,3008/14/2025On Time
Sequestration$0$0($718,300)($3,235,400)$0$0$0$0 N/A
Total$88,976,400$35,184,300($386,900)$19,761,500$14,299,400$8,638,000$14,100,100$5,661,400  

 

Army

STATUS OF SPECTRUM RELOCATION FUNDS
System/Program NameOriginal
Estimated
Transition
Costs
Adjusted
Estimated
Transition
Costs
SRF
Transfers
This
Reporting
Year
Total SRF
Transfers
Adjusted
System
Total
Cost Incurred
this Reporting
Year(Outlays)
Cumulative
Outlays
SRF BalanceSystem
Spending
Closeout
Date
Spending
Status
1695-1710 MHz Army deployment related costs$8,560,000$0$0$2,143,100$0$0$2,041,700$0 N/A
1695-1710 MHz Portal (ITS)$2,220,000$2,220,000$0$1,253,400$542,000$532,500$912,200$9,5009/14/2027On Time
AR-12 (Direct Readout Ground Station Hardening)N/A$18,496,000$200,000$8,893,600$201,100$200,000$8,892,500$1,1009/14/2027On Time
AR-13 (Fixed/Transportable Monitoring Systems) $43,155,000$4,960,000$24,836,000$4,960,400$4,960,000$24,374,800$4009/14/2027On Time
Cincinnati, OH - GOES RCVR$5,434,000$0$0$1,206,800$0$0$1,105,300$0 N/A
Columbus Lake, MS - GOES RCVR$5,434,000$0$0$1,206,800$0$0$1,105,300$0 N/A
Management, Oversite, Engineering Support (Army Spectrum Mgt Office)$250,000$250,000$0$925,000$425,000$75,000$400,000$350,0009/14/2027On Time
Monitoring System - Hub$13,138,200$0$0$3,500,500$0$0$3,398,700$0 N/A
Omaha, NE - GOES RCVR$5,360,400$0$0$1,191,300$0$0$1,089,800$0 N/A
Rock Island, IL - GOES RCVR$7,201,400$0$0$1,566,500$0$0$1,465,000$0 N/A
Sacramento, CA - GOES RCVR$5,655,000$0$0$1,252,000$0$0$1,150,500$0 N/A
Sequestration$0$0$0($1,705,300)$0$0$0$0 N/A
St Louis, MO - GOES RCVR$5,434,000$0$0$1,206,800$0$0$1,105,300$0 N/A
Vicksburg, MS - GOES RCVR$5,434,000$0$0$1,206,800$0$0$1,105,300$0 N/A
Total$64,121,000$64,121,000$5,160,000$48,683,300$6,128,500$5,767,500$48,146,400$361,000  

 

Department of the Navy (DON)

STATUS OF SPECTRUM RELOCATION FUNDS
System/Program NameOriginal
Estimated
Transition
Costs
Adjusted
Estimated
Transition
Costs
SRF
Transfers
This
Reporting
Year
Total SRF
Transfers
Adjusted
System
Total
Cost Incurred
this Reporting
Year(Outlays)
Cumulative
Outlays
SRF BalanceSystem
Spending
Closeout
Date
Spending
Status
1695-1710 MHz Portal (ITS)$2,220,000$2,220,000$419,600$1,593,600$661,300$0$383,800$661,3008/14/2025On Time
1695-1710 MHz Portal (Navy)$3,167,000$16,456,000$2,663,900$15,310,800$5,528,300$967,600$11,151,600$4,560,7008/14/2025On Time
DoN HQ Transition Process Management$3,136,000$3,136,000($104,100)$2,797,700$38,800$0$2,191,200$38,8008/14/2025On Time
METMF MetSat RCVR (USMC METOC-3) $25,347,000$2,296,500$17,690,400$14,221,100$6,949,500$9,808,500$7,271,6008/14/2025On Time
Monitoring – Hub$19,707,300$0($500)$840,500$0$0$0$0 N/A
Monterey MetSat RCVR (Navy METOC-3)$9,269,900$0($100)$674,800$0$0$0$0 N/A
Norfolk MetSat RCVR (Navy METOC-4) $2,980,000$75,200$2,969,000$2,270,500$578,900$1,157,900$1,691,6008/14/2025On Time
Pearl Harbor MetSat RCVR (Navy METOC-1)$18,706,400$3,009,000$0$3,009,000$2,005,900$407,800$1,114,800$1,598,1008/14/2025On Time
Sequestration $0($442,900)($5,959,900)$0$0$0$0 N/A
Stennis Space Center MetSat RCVR (Navy METOC-2)$9,269,900$0($100)$1,674,800$400$0$0$400 N/A
Test & Measurement System$0$0$0$0$0$0$0$0 N/A
Twenty-Nine Palms MetSat RCVR (USMC METOC-2)$5,434,000$0($100)$514,800$0$0$0$0 N/A
Yuma MetSat RCVR (USMC METOC-1)$5,434,000$0($100)$514,800$0$0$0$0 N/A
Total$76,344,500$53,148,000$4,907,300$41,630,300$24,726,300$8,903,800$25,807,800$15,822,500  

 

Department of Interior (DOI)

STATUS OF SPECTRUM RELOCATION FUNDS
System/Program NameOriginal
Estimated
Transition
Costs
Adjusted
Estimated
Transition
Costs
SRF
Transfers
This
Reporting
Year
Total SRF
Transfers
Adjusted
System
Total
Cost Incurred
this Reporting
Year(Outlays)
Cumulative
Outlays
SRF BalanceSystem
Spending
Closeout
Date
Spending
Status
Boise, ID - GOES (RRC BORPNRHA)$5,380,000$13,000,000$7,619,200$12,999,200$8,178,500$2,164,000$10,805,300$6,014,5009/23/2027On Time
Boise, ID - GOES (RRC NFIC)$5,380,000$13,000,000$7,619,200$12,999,200$8,133,200$2,164,000$9,559,600$5,969,2009/23/2027On Time
Guaynabo, PR - GOES (RRC CWSC)$8,189,000$8,189,000$0$8,189,000$0$0$27,500$012/23/2021Complete
Knoxville, TN - GOES (RRC TVARFC)$5,332,000$12,952,000$7,619,200$12,951,200$8,098,800$2,164,000$9,754,100$5,934,8009/23/2027On Time
Sioux Falls, SD - GOES (RRC EDDN-1)$0$0$0$0$0$0$0$0 N/A
Sioux Falls, SD - GOES (RRC EDDN-2)$0$0$0$0$0$0$0$0 N/A
Sioux Falls, SD - POES (RRC EROSLRPS)$10,044,000$17,664,000$7,619,200$17,663,200$8,178,600$2,164,000$10,722,200$6,014,6009/23/2027On Time
Total$34,325,000$64,805,000$30,476,800$64,801,800$32,589,100$8,656,000$40,868,700$23,933,100